Michigan Guide

    Michigan Construction Lien Deadlines

    Three numbers decide whether an unpaid contractor has leverage or just an invoice: 20, 90, and 365.

    Quick Answer

    What are the construction lien deadlines in Michigan?

    Michigan's Construction Lien Act sets three critical deadlines. First, a subcontractor or supplier must serve a notice of furnishing on the designee and general contractor named in the notice of commencement within 20 days after first furnishing labor or material (MCL 570.1109); a laborer's notice runs within 30 days after contractually due wages went unpaid. Second, a claim of lien must be recorded with the register of deeds in each county where the property is located within 90 days after the claimant's last furnishing, or the statute says the lien right ceases to exist (MCL 570.1111). Third, proceedings to enforce the lien through foreclosure must be brought no later than 1 year after the date the claim of lien was recorded, with a lis pendens recorded at filing (MCL 570.1117). A contractor with a direct contract with the owner or lessee does not need a notice of furnishing to preserve lien rights arising from that contract.

    Important: Clear Path Document Services is a document preparation and filing-assistance service — not a law firm. We do not provide legal advice, attorney representation, or create attorney-client relationships. All documents are prepared based on information you provide for educational and administrative purposes.Read full disclaimer.

    The sequence, in order

    1. Get the notice of commencement on day one

      It names the owner, the general contractor, and the designee, and it contains the legal description. Everything downstream depends on it. Ask for it before you start work, not after payment goes sideways.

    2. Serve the notice of furnishing within 20 days of first furnishing

      Subcontractors and suppliers serve the designee and general contractor named in the notice of commencement, personally or by certified mail. If no designee is named, serve the owner or lessee named there. Service by certified mail is complete on mailing.

    3. Laborers: 30 days after unpaid wages were due

      A laborer's notice of furnishing runs on a different trigger — within 30 days after wages were contractually due but not paid.

    4. Track your last furnishing date carefully

      The 90-day clock runs from the last day you furnished labor or material for the improvement under your contract. Warranty callbacks and punch-list visits are frequently argued about; do not assume a small return trip resets anything.

    5. Record the claim of lien within 90 days

      Record with the register of deeds in each county where the property sits. The lien is valid only as to the property described in it and located in that county. Get the legal description from the notice of commencement or the deed — a street address is not enough.

    6. Serve a copy of the recorded claim of lien

      A copy of the claim, along with the recorded proof of service of the notice of furnishing where one was required, must be served on the designee, or on the owner or lessee.

    7. Calendar the one-year enforcement deadline

      Foreclosure proceedings must be brought no later than 1 year after the date the claim of lien was recorded, and a notice of lis pendens is recorded when the action is filed. Miss it and the recorded lien stops being enforceable.

    8. Discharge the lien once you are paid

      Payment does not remove the lien. The claimant records a discharge with the same register of deeds. Owners: do not close a sale assuming it fell off on its own.

    Michigan construction lien timeline

    DeadlineWhoRuns fromStatute
    20 daysSubcontractor or supplier — notice of furnishingFirst furnishing of labor or materialMCL 570.1109
    30 daysLaborer — notice of furnishingDate contractually due wages went unpaidMCL 570.1109
    No notice requiredContractor with a direct owner or lessee contractN/A for that contract's lien rightsMCL 570.1109
    90 daysAll claimants — record claim of lienLast furnishing of labor or materialMCL 570.1111
    1 yearAll claimants — begin foreclosure proceedingsDate the claim of lien was recordedMCL 570.1117
    After paymentClaimant — record dischargePayment or settlementConstruction Lien Act

    General information about Michigan's Construction Lien Act, not legal advice. Whether a deadline has run in your situation is a legal question for an attorney.

    Key Terms

    Construction Lien Act
    Michigan Act 497 of 1980, which governs construction lien rights, notices, and enforcement.
    Notice of commencement
    The project document identifying the owner, general contractor, designee, and property description.
    Notice of furnishing
    The early notice preserving a subcontractor's, supplier's, or laborer's lien rights.
    Claim of lien
    The recorded document asserting the lien against the described property.
    Lis pendens
    A recorded notice that a lawsuit affecting the property has been filed.
    Common Questions

    People Also Ask

    Unpaid on a Michigan job?

    Send us your dates first — the timeline matters more than anything else. We prepare notices of furnishing, claims of lien, sworn statements, waivers, and discharges. Every matter is reviewed first, then we send a written quote.

    Not a law firm. We provide document preparation assistance only — no legal advice. Full disclaimer.

    Reviewed and updated by the Clear Path document team. Informational only — not legal advice.

    ClearPath Assistant

    Online • Available 24/7

    Hi there! 👋 I'm the Clear Path assistant. Ask me anything about Michigan court forms, our document preparation services, pricing, or what paperwork you need — I'll point you to the right place. Not sure where you fit? Tell me what's going on in your own words, or call or text us at (833) 777-FILE and we'll find a path that works for you.

    Prefer a person? Call (833) 777-FILE or text us.

    We are document preparers, not attorneys. Chat history is stored locally and auto-clears after 24 hours.